Sidford

This Project involved Drylining, Plastering, Plaster Boarding and MF Ceilings in all 40 Apartments that were a mixture of 1 and 2 bedrooms, we included cornice coving in all of the lounges, bedrooms and hallways. All of the apartments have metal stud walls which were also done by us. The owners Lounge has all of the above and then also Fibrous Cornice Coving. All of our sites we have worked on included metal stud walls.

We started working on this site in February 2020 and Finished it towards the end of 2020.

Thame

For this Project we did grid and tile ceilings, in all of the corridors throughout the building. We also did Fibrous Cornice in the owners lounge and then Cornice Coving in all of the Owners Apartments. On this site there were a total of 41 Apartments and in all of these we did all of the Drylining, Plastering, Plasterboarding, Metal Stud Walls and MF Ceilings. 

 

We started working on this site in 2019 in November and Finished towards the end of 2020 due to the pandemic

Reigate

This Project consisted of 31 apartments that were all Drylined, Plastered and Plaster boarded by us, we also did all of the MF ceilings and Cornice Coving was applied in every Lounge, Bedroom and Hallway and Metal Stud was used in all of the Wall Structures. In the Owners lounge we used Fibrous Cornice

We started working on this site in August 2019 and Finished this site by March 2020

Abingdon

This Project consisted of 39 apartments that were all Plastered, Plaster Boarded and Drylined by us. Metal Stud was used on all of the Wall Structures and Cornice Coving was applied in all of the Lounges, Hallways and Bedrooms. All Ceilings were done using MF. On this site we also did all of the outside rendering. In the Owners Lounge we used Fibrous Cornice

We started working on this site in November 2019 and Finished this site in August 2020

Yate

This was one of the largest Projects that our company has ever taken on consisting of 65 apartments and 6 cottages. On all of these apartments we did all of the Drylining, Plastering, Plasterboarding, MF ceilings, Metal Stud Walls and Cornice Coving and then in the owners lounge we used Fibrous Cornice.

We started working on this site in June 2019 and Finished this site in February 2020

Hythe

This was our most local project we have done, based in Southampton. This Project has a total of 43 Apartments,  as a company we did all of the Drylining, Plastering, Plasterboarding, MF ceilings, Metal Stud Walls and Cornice Coving and then In the owners lounge we used Fibrous Cornice.

We started working on this site in July 2020 and expect it to be finished around March of 2021

Previous Completed Churchills Projects

Due to the vast number of projects that we have worked on with Churchills Retirement Living and the similarity of the work that we do between each project, we decided to showcase some of our more recent projects above. To view more specific images of the work that was done by our company please visit the gallery page which can be found along the home bar at the top of this page. Alternatively If you click the PDF below you can view all of the sites that we have completed for Churchills Retirement Living, to view more information on these sites you can look at these via the Churchills Retirement Living Website. 